Step 1 of 16 6% Name* First Company Name* First Designation* First Phone*Email* What is the Scrum approach about doing design early in a project?* A big design upfront is always a good idea Just enough design upfront gives a good foundation to start from and helps to mitigate the risk with out wasting unnecessisarly time. No design upfront is the best approach as most of the fun of a project is in discovery of the excepted. No deign required in scrum What is Scrum?* A method A course book A Framework A Note book In which meeting the key stake holders are usually participate?* The sprint planning The Sprint review Restrospection Daily scrum What happens at the end of every the sprint ?* Completed work Scope covered A Done Increment is created Quality Work The time-box for a Daily Scrum is?* Two minutes per person. 15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter. 4 hours. 15 minutes. Product backlog must have user stories.* False True What is the most impotant in all Scrum projects? 1. Self organization 2. Clear hirarchies in the company 3. communication 4. Continuous improvement* 1,2,3 1,3,4 1,2,3,4 1,2 What is DoD?* Define on Define Done on Done Definition of Done Done other Done Which of the below is not a scrum master responsibility?* Assigning tasks to team members Reminding the team of the process Removing impediment Facilitating meetings The definition of done can be reviewed and adapted during each sprint retrospective.* True False Who determines whether the development team has been assigned enough work in a sprint?* The product owner and the scrum master The scrum master The product Owner The Development Team Which of the following is not a scrum life cycle activity?* Sprint Retrospection Weekly Inspection Sprint Planning Daily Scrum The Agile/Scrum approach to documentation is?* Do no documentation because it is a waste of time Do the necessary documentation to support the development and use of the project Do suficient documentation to prove you have a good job Dore documentation than usual , because agile is easy During a sprint the developers should be?* In twice- daily contact with the product owner Completely be uninterrupted by the product owner Should be working with PO as needed to keep the sprint goal realistic Able to work without needing to disturb the product owner Which of the following is a characteristic of a Scrum master?* Task focused Process oriented Supportive Disengaged